Gila County’s Stagecoach Trail project in Roosevelt will commence Wednesday, February 5.
This item is available in full to subscribers.
To continue reading, you will need to either log in to your subscriber account, below, or purchase a new subscription.
Please log in to continue |
Gila County’s Stagecoach Trail project in Roosevelt will commence Wednesday, February 5.
The project will remove the existing pavement, grade the roadway, and construct new pavement, ribbon curb and a valley gutter along Stagecoach Trail from about Spur Trail to White Wing Drive. Work will take about 60 calendar days to complete, with an estimated completion date of Friday, April 5, 2024. During that time, there will be traffic control and detours for the various stages of work.
Gila County will have a project manager on site during work hours to answer questions.
You may also contact 928-402-4225 or projects@gilacountyaz.gov if you have any questions.